Overview
The project of State significance proposes a multipurpose stadium at Macquarie Point (the project).
The project is subject to an integrated assessment process under the State Policies and Projects Act 1993 (the Act) and the requirements of the Ministerial Direction issued under the Act.
This is the second stage of the process, where the Commission prepares an integrated assessment report with recommendations to the Minister.
See Macquarie Point Multipurpose Stadium Guidelines for information about the first stage of the process.
Received
The Commission has received the proponent’s reports in response to the Guidelines, submitted on 17 September 2024. The Commission has now commenced the integrated assessment of the project.
The Commission must prepare its integrated assessment report within 12 months of the submission date, or such later day as the Minister may direct in writing.
The proponent’s reports are provided for information below.
The Commission is required to consult with Hobart City Council and identified agencies with an interest in the project in relation to the preparation of the draft integrated assessment report.
The Panel has determined the agencies considered to have an interest in the project. See the list of agencies (PDF, 76.3 KB).
The overall assessment process is summarised in a flowchart (PDF, 181.6 KB).
Proponent’s further information reports - post 4 March 2025
Macquarie Point Development Corporation further information request response letter 21 May 2025 06/08/2026 The Goods Shed initial conservation management plan 16 May 2025 06/08/2026 Macquarie Point Development Corporation further information request response letter 8 May 2025 06/08/2026 Annexure - A Stormwater Assessment 8 May 2025 06/08/2026Proponent’s further information reports - 4 March 2025
Macquarie Point Development Corporation further information request response letter 4 March 2025 06/08/2026 Annexure A - Macquarie Point Development Corporation request for further information response table 4 March 2025 06/08/2026 Annexure B - Updated architectural plans (MPMS-CXC-DR-01-A20-0050-P3 Gantry Level and MPMS-CXC-DR-01-A20-0060 P3 Roof Plan 4 March 2025 06/08/2026 Annexure C - AECOM Australia response on Wind 4 March 2025 06/08/2026Proponent’s further information reports - 17 February 2025
Macquarie Point Development Corporation further information request response letter 17 February 2025 06/08/2026 Annexure A - Macquarie Point Development Corporation request for further information response table 17 February 2025 (SUPERSEDED by Annexure A dated 4 March 2025) 06/08/2026 Annexure B - Consolidated plans 1 17 February 2025 06/08/2026 Annexure B - Consolidated plans 2 17 February 2025 (architectural plans MPMS-CXC-DR-01-A20-0050 Gantry Level and MPMS-CXC-DR-01-A20-0060 Roof Plan SUPERSEDED by Annexure B dated 4 March 2025) 06/08/2026 Annexure B - Consolidated plans 3 17 February 2025 06/08/2026 Annexure B - Consolidated plans 4 17 February 2025 06/08/2026 Annexure C - Ireneinc Planning and Urban Design Planning Report 17 February 2025 06/08/2026 Annexure D - SLR viewpoint locations information 17 February 2025 06/08/2026 Annexure E - GJM Heritage and Purcell Architecture heritage response 17 February 2025 06/08/2026Proponent’s further information reports - 14 February 2025
Macquarie Point Development Corporation further information request response letter 14 February 2025 06/08/2026 Annexure A - Macquarie Point Development Corporation request for further information response table 14 February 2025 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Annexure B - Zancon Construction Management Plan comments – carpark construction and site dewatering management 14 February 2025 06/08/2026 Annexure C - Cox Architecture Information on Gross Floor Areas 12 February 2025 06/08/2026Proponent’s further information reports - 31 January 2025
Macquarie Point Development Corporation further information request response letter 31 January 2025 06/08/2026 Annexure A - Macquarie Point Development Corporation request for further information response table 31 January 2025 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Annexure B - Consolidated plans 31 January 2025 (SUPERSEDED by Annexure B dated 17 February 2025) 06/08/2026 Annexure B - Consolidated plans 2 31 January 2025 (SUPERSEDED by Annexure B dated 17 February 2025) 06/08/2026 Annexure C - BMG supporting statement detailed design stage plans 29 January 2025 06/08/2026 Annexure D - Jensen Hughes supporting statement concept design 31 January 2025 06/08/2026 Annexure E - Zancon supporting statement detailed design stage plans 28 January 2025 06/08/2026 Annexure G - Macquarie Point Development Corporation economic societal costs and benefits 31 January 2025 06/08/2026 Annexure H - KPMG Economics Analysis Report 31 January 2025 06/08/2026 Annexure I - Wolferstan Verney and Partners Pty Ltd Economics Analysis Report cost estimates 31 January 2025 06/08/2026 Annexure J - Macquarie Point Development Corporation Draft Precinct Plan Consultation Summary 31 January 2025 06/08/2026 Annexure K - SLR Consulting visualisations 31 January 2025 06/08/2026 Annexure L - SLR Consulting clarification regarding visualisation 31 January 2025 06/08/2026 Annexure M - Macquaire Point Development Corporation Aboriginal community consultation 31 January 2025 06/08/2026 Annexure N - Tasmanian Aboriginal community engagement and Aboriginal Culturally Informed Zone and Stadium August 2024 06/08/2026 Annexure O - Southern Archaeology Aboriginal Heritage Assessment Report 30 January 2025 06/08/2026 Annexure P - WSP transport and movement matters 31 January 2025 06/08/2026 Annexure Q - AECOM Australia Noise Assessment supplementary report 31 January 2025 06/08/2026 Annexure R - Introba Lighting Assessment 31 January 2025 06/08/2026 Annexure S - AECOM Australia environmental condition of the site 31 January 2025 06/08/2026 Annexure T - BMT stormwater management 31 January 2025 06/08/2026 Annexure U - Tetra Tech Coffey Environmental Auditor opinion 30 January 2025 06/08/2026 Annexure V - Macquarie Point Development Corporation emergency management and incident response January 2025 06/08/2026 Annexure W - Subdivision plan 31 January 2025 06/08/2026 Annexure X - SBP statement regarding the roof structure 20 December 2024 06/08/2026 Annexure Y - Summary on opportunity for commercial tenancies 31 January 2025 06/08/2026 Annexure Z - Key components cost spreadsheet 31 January 2025 06/08/2026Proponent's reports
Macquarie Point Multipurpose Stadium Summary Report September 2024 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A00-0000_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A11-0000_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A11-1000_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A15-1000_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A20-0000_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A20-0010_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A20-0020_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A20-0021_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A20-0030_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A20-0040_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A20-0050_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A20-0100_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A30-0010_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A30-0020_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A40-0000_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix A - Architectural Drawings MPS-COX-DR-01-A80-0000_P1 (SUPERSEDED by Annexure A dated 17 February 2025) 06/08/2026 Appendix AA - Construction Management Plan - ZANCON August 2024 06/08/2026 Appendix B - Stadium Design Description - COX+Cumulus August 2024 06/08/2026 Appendix B - Stadium Design Description 2 - COX+Cumulus August 2024 06/08/2026 Appendix BB - Services Report - Infrastructure Strategy - JMG August 2024 06/08/2026 Appendix C - Housing for Workforce - LeftField Project Solutions 06/08/2026 Appendix CC - Emergency Management and Incident Response - Intelligent Risks Pty Ltd August 2024 06/08/2026 Appendix D - Cut and Fill - WSP 7 August 2024 06/08/2026 Appendix DD - Title folio plans and easements relating to project site 24 July 2024 06/08/2026 Appendix E - Cost Benefit Analysis - KPMG 5 September 2024 06/08/2026 Appendix EE - Car Parking & Access Review - SALT 4 September 2024 06/08/2026 Appendix F - Economic Impact Assessment - KPMG 5 September 2024 06/08/2026 Appendix FF - Conceptual Hydrogeological Model and Numerical Model Memo - Hydro Earth Consulting 17 July 2024 06/08/2026 Appendix G - Financial Impact Report - KPMG 9 September 2024 06/08/2026 Appendix GG - Site Development Plan - Brian Risby April 2024 06/08/2026 Appendix H - Social and Cultural Analysis Report - KPGM 9 September 2024 06/08/2026 Appendix HH - Pre-Stadium Cultural and Landscape Values Assessment - Southern Archaeological 28 August 2024 06/08/2026 Appendix I - Urban Design Framework August 2024 06/08/2026 Appendix II - Geotechnical Factual Report - WSP June 2024 06/08/2026 Appendix J - Visual Impact Assessment Report - SLR Consulting 30 August 2024 06/08/2026 Appendix JJ - Mac Point Precinct Plan - Macquarie Point Development Corporation August 2024 06/08/2026 Appendix K - Previous Aboriginal Heritage Investigations - 17 July 2024 06/08/2026 Appendix KK - Preliminary Results of Acid Sulphate Investigation - AECOM 2 August 2024 06/08/2026 Appendix L - Historic Cultural Heritage Impact Assessment - Purcell and GJM Heritage August 2024 06/08/2026 Appendix LL - Site Environment Management Plan - AECOM 22 October 2021 06/08/2026 Appendix M - Historical Archaeological Assessment, Sensitivity Report and Method Statement - Aboriginal Heritage Investigations 20 August 2024 06/08/2026 Appendix MM - AFL Licence Taskforce Business Plan 2019 - 18 December 2019 06/08/2026 Appendix N - Transport Study - WSP August 2024 06/08/2026 Appendix NN - Public Art Strategy Discussion Paper - Inkhorn Projects September 2024 06/08/2026 Appendix O - Wind Comfort Assessment for Visitors and the Precinct Area - Wacker Ingenieure 21 August 2024 06/08/2026 Appendix P - Lighting Assessment and Electrical & Hydraulic Infrastructure - Introba 4 September 2024 06/08/2026 Appendix Q - Noise and Vibration Assessment - AECOM 21 August 2024 06/08/2026 Appendix R - Natural Values Assessment - North Barker 27 August 2024 06/08/2026 Appendix S - Stormwater Management Plan - BMT 26 August 2024 06/08/2026 Appendix T - Solid Waste and Hazardous Material Management - Incognitus August 2024 06/08/2026 Appendix U - Coastal Inundation Assessment - BMT 23 August 2024 06/08/2026 Appendix V - Site Remediation Strategy Update 2024 - AECOM 17 June 2024 06/08/2026 Appendix W - Overland Flood Assessment - BMT 23 August 2024 06/08/2026 Appendix X - Geotechnical Interpretive Report - WSP July 2024 06/08/2026 Appendix Y - Heat Risk and Climate Change Assessment - BMT 31 May 2024 06/08/2026 Appendix Z - Signs - Futago 27 August 2024 06/08/2026Stakeholder communications
Commission email to Department of Premier and Cabinet requesting additional cost information for stadium 2 July 2025 06/08/2026 Commission email to Department of Premier and Cabinet - response to Technical Note 1 27 June 2025 06/08/2026 Email and document from Department of Premier and Cabinet responding to Commission email regarding updated capital cost estimates - Technical Note Number 1 - 25 June 2025 06/08/2026 Commission email to Department of Premier and Cabinet with updated capital cost estimates 24 June 2025 06/08/2026 Letter from MinterEllison providing details of witnesses for hearing 17 June 2025 06/08/2026 Letter from MinterEllison stating time needed to represent at the hearing 16 June 2025 06/08/2026 Commission letter to MinterEllison responding to request to adjourn hearing 17 June 2025 06/08/2026 Letter from MinterEllison requesting to adjourn hearing 13 June 2025 06/08/2026 Commission email to Department of Premier and Cabinet - updated capital cost estimates 12 June 2025 06/08/2026 Commission email to Department of Premier and Cabinet acknowledging receipt of draft enabling legislation 30 May 2025 06/08/2026 Letter from Department of Premier and Cabinet providing draft enabling legislation 27 May 2025 06/08/2026 Commission letter to Department of Premier and Cabinet 23 May 2025 06/08/2026 Letter from Department of Premier and Cabinet 21 May 2025 06/08/2026 Commission email to MinterEllison and Macquarie Point Development Corporation advising of publication of representations to website 16 May 2025 06/08/2026 Commission email to MinterEllison and Macquarie Point Development Corporation providing update on representations 12 May 2025 06/08/2026 Letter from Macquarie Point Development Corporation providing update on outstanding reports 7 May 2025 06/08/2026 Commission email to Macquarie Point Development Corporation on outstanding reports 30 April 2025 06/08/2026 Commission letter to MinterEllison on integrity of draft Intregrated Assessment Report 15 April 2025 06/08/2026 Commission letter to MinterEllison responding to representation 8 April 2025 06/08/2026 Representation MinterEllison for the Crown in Right of Tasmania 3 April 2025 06/08/2026 Commission email to Macquarie Point Development Corporation advising indicative exhibition and hearings timeline 11 March 2025 06/08/2026 Commission email to Macquarie Point Development Corporation requesting further information on 3D Model of Stadium Project 27 February 2025 06/08/2026 Commission email to Macquarie Point Development Corporation Scope of Assessment 22 January 2025 06/08/2026 Commission letter to Macquarie Point Development Corporation requesting further information 19 November 2024 06/08/2026 Commission letter to relevant agencies 26 September 2024 06/08/2026 Commission letter to Hobart City Council 25 September 2024 06/08/2026 Commission email to Environment Protection Authority 2 August 2024 06/08/2026 Commission email to Heritage Tasmania 2 August 2024 06/08/2026 Commission email to Department of Treasury and Finance 23 July 2024 06/08/2026 Commission email to Department of State Growth 23 July 2024 06/08/2026 Commission email to Hobart City Council 23 July 2024 06/08/2026 Commission letter to relevant agencies 11 April 2024 06/08/2026 Commission letter to Macquarie Point Development Corporation (as a relevant agency) 11 April 2024 06/08/2026 Commission letter to Hobart City Council 11 April 2024 06/08/2026 Commission letter to Department of Premier and cabinet 11 April 2024 06/08/2026 Commission letter to Department of Climate Change Energy the Environment and Water 11 April 2024 06/08/2026 Commission letter to Macquarie Point Development Corporation on integrated assessment process 22 February 2024 06/08/2026Stakeholder meetings
Stakeholder meeting with Macquarie Point Development Corporation 17 January 2025 06/08/2026 Stakeholder meeting with Macquarie Point Development Corporation 18 June 2024 06/08/2026 Stakeholder meeting with Macquarie Point Development Corporation 29 February 2024 06/08/2026Supporting material
Macquarie Point Multipurpose Stadium Integrated Assessment Process Flowchart 22 February 2024 06/08/2026 Ministerial direction 16 October 2023 06/08/2026 State Policies and Projects (Project of State Significance) Order 2023 06/08/2026 Tasmanian Government Gazette 16 October 2023 06/08/2026 Disclosure of Interests and Associations as at 28 November 2023 06/08/2026 Guidance on process, representations and hearings 06/08/2026 List of relevant agencies 06/08/2026Exhibition
The exhibition and representation period have now closed.
Exhibition of the draft integrated assessment report (draft IAR) commences at 4pm on 31 March 2025.
Representations may be made to the Commission until 8 May 2025 via the representation form.
Written representations must be received no later than midnight on 8 May 2025. Late representations will not be accepted.
Representations may also be submitted by post to Tasmanian Planning Commission, GPO Box 1691, HOBART TAS 7001.
The draft IAR, submissions from Hobart City Council and relevant agencies, and the Proponent's reports are available to view and download.
The draft IAR, submissions and the Proponent’s reports may also be viewed in person at:
- Tasmanian Planning Commission offices, Level 3, 144 Macquarie Street, Hobart (from 9am until 5pm, Monday to Friday)
- Launceston Library, 71 Civic Square, Launceston (during opening hours)
- Devonport Library, Paranaple Centre, 137 Rooke Street, Devonport (during opening hours)
- Burnie Library, 30 Alexander Street, Burnie (during opening hours)
Further information is available in the FAQ's.
Exhibition of draft integrated assessment report under section 22 of the State Policies and Projects Act 1993
The draft IAR is on exhibition during this period. The draft IAR, submissions from Hobart City Council and relevant agencies, and a consolidated set of the Proponent’s plans for the Project are available below. The Proponent’s reports addressing a range of issues relating to the Project are available under ‘Received’ above.
Public notice 31 March 2025Exhibition documents
Macquarie Point Multipurpose Stadium Draft Integrated Assessment Report 31 March 2025 06/08/2026Agency submissions
Submission TasWater 7 October 2024 06/08/2026 Submission NBN Co Limited 22 October 2024 06/08/2026 Submission Clarence City Council 23 October 2024 06/08/2026 Submission Stadiums Tasmania 23 October 2024 06/08/2026 Submission Marine and Safety Tasmania 23 October 2024 06/08/2026 Submission TasPorts 23 October 2024 06/08/2026 Submission Department of State Growth 24 October 2024 06/08/2026 Submission Environment Protection Authority 24 October 2024 06/08/2026 Submission TasNetworks 25 October 2024 06/08/2026 Submission Macquarie Point Development Corporation 25 October 2024 06/08/2026 Submission Australian Antarctic Division 1 November 2024 06/08/2026 Submission University of Tasmania 8 November 2024 06/08/2026 Submission Tasmanian Heritage Council 11 November 2024 06/08/2026 Submission Hobart City Council 12 November 2024 06/08/2026Current Proponent plans
Consolidated plans 1 - 4 March 2025 06/08/2026 Consolidated plans 2 - 4 March 2025 06/08/2026 Consolidated plans 3 - 4 March 2025 06/08/2026 Consolidated plans 4 - 4 March 2025 06/08/2026Hearing
Please note the Commission will consider every representation but will not necessarily hold a hearing into every one. It is anticipated that a number of issues raised by some of the representations will be the subject of hearings.
Directions hearing
Merino Room, The Old Woolstore Hotel, 1 Macquarie Street, Hobart
Directions hearing summary 10 June 2025Hearing (multiple dates)
Merino Room, The Old Woolstore Hotel, 1 Macquarie Street, Hobart
25-27 June, 30 June, 1-3 July, 7-11 July and 15 July (commencing 9.30am)
Hearing Schedule current as at 11 July 2025Hearing and further submissions
Submission MinterEllison response to SES submission 5 September 2025 06/08/2026 Submission SES Stormwater Assessment Report 21 August 2025 06/08/2026 Submission MinterEllison proposed permit conditions 31 July 2025 06/08/2026 Submission MinterEllison permit plans consolidated 31 July 2025 Part 1 06/08/2026 Submission MinterEllison permit plans consolidated 31 July 2025 Part 2 06/08/2026 Submission Greg Lehman 3 July 2025 06/08/2026 Submission MinterEllison Design integrity cases supporting draft conditions 14 July 2025 06/08/2026 Submission - MinterEllison - proposed permit conditions 11 July 2025 06/08/2026 Submission MinterEllison correspondence between MinterEllison Brendon Gale and Damian Gill on AFL funding package 15 July 2025 06/08/2026 Submission Roland Browne Our Place closing submission 15 July 2025 06/08/2026 Submission - MinterEllison - Landscape plans including names of architects and sub-consultants 14 July 2025 06/08/2026 Submission - MinterEllison - Technical Note 16 - Reconciliation of Plans 14 July 2025 06/08/2026 Submission - MinterEllison - Technical Note 15 - Aboriginal Community Consultation and Engagement 14 July 2025 06/08/2026 Submission - MinterEllison - Technical Note 14 - Tourism Data 14 July 2025 06/08/2026 Submission - MinterEllison - email on proposed permit conditions 10 July 2025 06/08/2026 Submission - MinterEllison - proposed permit conditions 10 July 2025 06/08/2026 Submission - MinterEllison GJM Heritage letter to MinterEllison on proposed heritage permit conditions 10 July 2025 06/08/2026 Submission - MinterEllison - email with addendum to noise & vibration evidence, landscape plans authorship and response on transport modelling 10 July 2025 06/08/2026 Submission - MinterEllison - Dr Neil Mackenzie - Noise and Vibration Addendum to Statement of Expert Evidence 10 July 2025 06/08/2026 Submission - Roland Browne Our Place - hearing opening statement 9 July 2025 06/08/2026 Submission - MinterEllison - Technical Note 13 - Emergency Management and Safety 9 July 2025 06/08/2026 Submission - MinterEllison - Technical Note 12 - Power supply infrastructure 9 July 2025 06/08/2026 Submission - MinterEllison - Correspondence between MinterEllison Brendon Gale and Damian Gill regarding AFL funding package 9 July 2025 06/08/2026 Submission - Hobart City Council 9 July 2025 06/08/2026 Submission - MinterEllison - Technical Note 11 - Site Remediation 8 July 2025 06/08/2026 Submission - MinterEllison - Technical Note 10 - Landscape Plans 8 July 2025 06/08/2026 Submission - MinterEllison - Technical Note 10 - Attachment 1 - Current landscape concept plans 8 July 2025 06/08/2026 Submission - MinterEllison - Technical Note 9 - Precinct Car park 8 July 2025 06/08/2026 Submission - Roland Browne Our Place - Timothy Biles Tim Biles Project - Addendum to hearing presentation 9 July 2025 06/08/2026 Submission - Ian Terry - Hobart War Memorial paper 2002 06/08/2026 Submission - Ian Terry - Cenotaph Report final January 2001 06/08/2026 Submission - Ian Terry - Shrine of Remembrance July 2013 06/08/2026 Submission - Dr Naomi Parry Duncan hearing presentation 8 July 2025 06/08/2026 Submission - MinterEllison - Technical Note 8 - Additional operating model and capital cost information 8 July 2025 06/08/2026 Submission - MinterEllison - KPMG hearing presentation 8 July 2025 06/08/2026 Submission - MinterEllison - Correspondence with Brendon Gale regarding AFL funds distribution 7 July 2025 06/08/2026 Submission - letter MinterEllison 7 July 2025 06/08/2026 Submission - MinterEllison - Jim Gard'ner Historic Heritage Addendum to Statement of Evidence 7 July 2025 06/08/2026 Submission - MinterEllison - Jim Gard'ner hearing presentation 8 July 2025 06/08/2026 Submission - MinterEllison - Technical Note 7 - Northern Access Road and Bus Plaza 7 July 2025 06/08/2026 Submission - MinterEllison - Technical Note 6 - Cricket specific design elements and roof design testing 7 July 2025 06/08/2026 Submission - MinterEllison - Graeme Steverson WSP hearing presentation 7 July 2025 06/08/2026 Submission - letter MinterEllison 3 July 2025 06/08/2026 Submission - MinterEllison - Technical Note 5 - Plans Update and Clarification 3 July 2025 06/08/2026 Submission - Stadiums Tasmania hearing presentation 3 July 2025 06/08/2026 Submission - Jerry de Gryse 1 July 2025 06/08/2026 Submission - Environment Protection Authority 1 July 2025 06/08/2026 Submission - MinterEllison - Cox Architecture hearing presentation - Design Overview - Egress Diagrams June 2025 06/08/2026 Submission - letter MinterEllison 1 July 2025 06/08/2026 Submission - MinterEllison - Technical Note 4 - Federal Funding Agreement 1 July 2025 06/08/2026 Submission - Graeme Wells - Comments on KPMG Consolidated Report 30 June 2025 06/08/2026 Submission - Hobart City Council - Professor Peter Phibbs - AEC Response to Peer Review 30 June 2025 06/08/2026 Submission - Visual Impact Assessment agreement between Mr Goss Orbit Solutions Mr Saul and Mr Murphy 30 June 2025 06/08/2026 Submission - letter MinterEllison 30 June 2025 06/08/2026 Submission - MinterEllison - Neil Shephard - Planning Statement of Evidence 29 June 2025 06/08/2026 Submission - letter MinterEllison 29 June 2025 06/08/2026 Submission - MinterEllison - Technical Note 3 - Precinct Plan 29 June 2025 06/08/2026 Submission - Roland Browne Our Place - Barry Murphy Murphy Landscape Consultancy - Landscape Architecture Evidence hearing presentation 9 July 2025 06/08/2026 Submission - Roland Browne Our Place - Timothy Biles Tim Biles Project - Report 1 Review and Conclusions and Report 2 Analysis of Renders and Montages April 2025 06/08/2026 Submission - Roland Browne Our Place - Barry Murphy Murphy Landscape Consultancy - review of Orbit Solutions expert evidence 29 June 2025 06/08/2026 Submission - MinterEllison - Cox Architecture hearing presentation 1 30 June 2025 07/08/2026 Submission - MinterEllison - Cox Architecture hearing presentation 2 - Plaza Entry 30 June 2025 Submission - MinterEllison - Cox Architecture hearing presentation 3 - video of shadow condition - Midday 15th May 2025 Submission - MinterEllison - Cox Architecture hearing presentation 4 - Inside the Stadium 30 June 2025 Submission - Brendon Gale - Tasmania Football Club - hearing presentation 27 June 2025 06/08/2026 Submission - MinterEllison - Technical Note 2 Capacity for approval 26 June 2025 06/08/2026 Submission - MinterEllison - Kim Evans hearing presentation 27 June 2025 06/08/2026 Submission - MinterEllison - KPMG consolidated report 26 June 2025 06/08/2026 Submission - letter MinterEllison 25 June 2025 06/08/2026 Submission - MinterEllison - Christopher Goss Orbit Solutions - Landscape and Visual Impact Assessment 25 June 2025 06/08/2026 Submission - MinterEllison - Christopher Goss Orbit Solutions - visual amenity evidence statement photomontages 24 June 2025 07/08/2026 Submission - MinterEllison - Christopher Goss Orbit Solutions - visual amenity statement of evidence 24 June 2025 06/08/2026 Submission - MinterEllison - Technical Note 1 - updated capital cost estimates 24 June 2025 06/08/2026 Submission - MinterEllison - correspondence between the State and Cricket Australia and Cricket Tasmania in respect of the Heads of Agreement 25 June 2025 06/08/2026 Submission - MinterEllison - MinterEllison letter to Department of State Growth seeking further information on proposed Northern Access Road 24 February 2025 06/08/2026 Submission - MinterEllison - Department of State Growth letter to MinterEllison providing further information on proposed Northern Access Road 7 April 2025 06/08/2026 Submission - MinterEllison - Sullivans Cove Planning Review 1991 07/08/2026 Submission - MinterEllison - Precinct Plan 25 June 2025 06/08/2026 Submission - letter MinterEllison 24 June 2025 06/08/2026 Submission - MinterEllison - general submission 24 June 2025 06/08/2026 Submission - letter MinterEllison 23 June 2025 06/08/2026 Submission - MinterEllison - Graeme Steverson - Transport statement of evidence 21 June 2025 06/08/2026 Submission - Cricket Australia and Cricket Tasmania 20 June 2025 06/08/2026 Submission - Tasmanian Symphony Orchestra 19 June 2025 06/08/2026 Submission - letter MinterEllison 19 June 2025 06/08/2026 Submission - MinterEllison - Dr Neil Mackenzie - Noise & Vibration statement of evidence 18 June 2025 06/08/2026 Submission - MinterEllison - Jim Gard'ner - Historic Heritage statement of evidence 18 June 2025 06/08/2026 Submission - Cuan Petheram 17 June 2025 06/08/2026 Submission - Hobart City Council 16 June 2025 06/08/2026Decision
Commission reports to the Minister
The Panel has finalised its integrated assessment report, and a recommendation report to the Minister under section 26 of the State Policies and Projects Act 1993.
Commission letter of transmission to the Minister - 16 September 2025FAQs