Current status - last updated 13/03/2026 :Completed

Overview

The major project proposes use and development for a wind farm and associated infrastructure located northwest of Bothwell, east of Tarraleah and north of Hamilton.

It comprises up to 56 wind turbine generators and associated hardstands, a battery energy storage system, electricity reticulation, connection to an existing transmission line, substation and switchyard, access roads, carparking, buildings and associated infrastructure, temporary construction facilities including construction compound, concrete batching plant and quarries on a site of approximately 8,460 hectares.

This is the first stage of the major project assessment process under the Land Use Planning and Approvals Act 1993 (the Act). If the Development Assessment Panel (the Panel) considers the major project has a reasonable prospect, based on advice from relevant regulators, the Panel prepares and exhibits draft assessment criteria for public comment.

You can view the next stage of this major project assessment process on our website.

Received

The Commission received a notice from the Minister for Housing, Planning and Consumer Affairs of the declaration of the major project under section 60R of the Act. The notification included a copy of the major project proposal.

31 January 2025

Commission receives notice from the Minister for Planning under section 60R

The Commission received a notice from the Minister for Housing, Planning and Consumer Affairs of the declaration of the major project under section 60R of the Act. The notification included a copy of the major project proposal.

State Planning Office - Notice of declaration of project 31 January 2025 PDF, 213.0 KB

Exhibition

Representations can be made to the Commission until 30 July 2025 by email to tpc@planning.tas.gov.au or post to Tasmanian Planning Commission, GPO Box 1691, Hobart 7001.

17 July 2025 - 30 July 2025

Exhibition of draft assessment criteria for the major project under section 60ZL

The draft assessment criteria and draft MNES guidelines are on exhibition during this period. All exhibition documents are available below.

Public notice 16 July 2025 PDF, 71.7 KB

The number of representations received during this exhibition: 14

Decision

18/09/2025

Panel determines assessment criteria

The Panel determined the assessment criteria and MNES guidelines for the Cellars Hill Wind Farm Major Project under section 60ZM of the Act on 18 September 2025.

Assessment criteria and MNES guidelines - Cellars Hill Wind Farm Major Project 18 September 2025 PDF, 628.8 KB