Current status - last updated 03/09/2024 :Completed

Overview

The major project proposes use and development for wind farms and associated infrastructure at the West Coast, centred around Lake Pieman, extending south to Zeehan and Trial Harbour, west towards Granville Harbour, east towards Renison Bell and north towards Mt Livingston. It comprises approximately 500 wind turbine generators, associated hardstands, access roads, electricity reticulation, substations, office and workshop facilities, temporary construction facilities including construction compounds, concrete batching plants, quarry and bunded refuelling facilities.

This is the first stage of the major project assessment process under the Land Use Planning and Approvals Act 1993 (the Act). If the Development Assessment Panel (the Panel) considers the major project has a reasonable prospect, based on advice from relevant regulators, the Panel prepares and exhibits draft assessment criteria for public comment.

Received

The Minister for Planning provided notice to the Commission of the declaration of the major project under section 60R of the Act. The notification included a copy of the major project proposal.

06/03/2024

Commission receives notice from the Minister for Planning under section 60R

The Minister for Planning provided notice to the Commission of the declaration of the major project under section 60R of the Act. The notification included a copy of the major project proposal.

Minister for Planning - Notice of declaration of project 6 March 2024 PDF, 144.5 KB

Exhibition

Representations can be made to the Commission until 15 July 2024 by email to tpc@planning.tas.gov.au or post to Tasmanian Planning Commission, GPO Box 1691, Hobart 7001

30/06/2024 - 15/07/2024

Exhibition of draft assessment criteria for the major project under section 60ZL

The draft assessment criteria are on exhibition during this period. All exhibition documents are available below.

Public notice 29 June 2024 PDF, 85.2 KB

The number of representations received during this exhibition: 11

Decision

21/08/2024

Panel determines assessment criteria

The Panel determined the assessment criteria for the Whaleback Ridge Renewable Energy Major Project under section 60ZM of the Act on 21 August 2024

Assessment criteria - Whaleback Ridge Renewable Energy Major Project - 21 August 2024 PDF, 447.1 KB
Back to top