Contents
Draft Impact Assessment Statement
Public Exhibition of the Draft Integrated Impact Assessment Statement
Public Hearing of the Draft Integrated Impact Assessment Statement
Draft Panel Report
Public Exhibition of the Draft Panel Report
Public Hearing of the Draft Panel Report
The Draft Integrated Impact Assessment Statement (IIAS) has been prepared by Basslink Pty Ltd in accordance with the Final Scope Guidelines published by the Joint Advisory Panel (established to carry out the assessment of the Basslink proposal) in October 2000.
The Draft Integrated Impact Assessment Statement (IIAS) has been submitted to the Joint Advisory Panel for assessment.
The IIAS addresses all issues identified in the Final Scope Guidelines. The IIAS includes:
Public exhibition of Draft IIAS and submissions received
The Draft IIAS was placed on public exhibition from 2 July 2001 to 31 August 2001. Advertisements were placed in State and national newspapers notifying the public that the Draft IIAS was available to be viewed at various locations, including the internet, and copies were available for purchase from the proponent. The 59 technical reports and studies prepared in the course of preparing the Draft IIAS were also made available to the public. The Panel received 536 submissions from government and non government organisations, community interest groups and individuals. These submissions were each recorded and acknowledged.
Panel hearing in Tasmania and Victoria
The Panel invited all submitters to present their submission at a hearing. A public hearing has been held in Tasmania and Victoria to better inform the Panel about the issues raised in submissions on the Draft IIAS. The hearing was held at George Town and Hobart in Tasmania and Traralgon and Yarram in Victoria. A total of 139 presentations were made during the public hearing. Documents tabled at the hearing were numbered and available for public inspection.
The Joint Advisory Panel has prepared a Draft Panel Report on the Basslink proposal. The Draft Panel Report contains the Panel’s preliminary findings on whether the project should be approved and, if so on what conditions, including draft recommendations, draft conditions and permits and approvals.
Public comment period commences 12 March and closes 16 April 2002
The Joint Advisory Panel prepared a Draft Panel Report on the Basslink proposal.
Interested persons and organisations were invited to comment in writing on the Draft Panel Report, in particular on the draft recommendations, draft conditions, permits and approvals.
A copy of the Draft Panel Report was mailed to all people who made a presentation at the Panel hearing on the Basslink Draft Integrated Impact Assessment Statement.
The Panel may hold further public hearings in both Victoria and Tasmania.
Back to: Assessment process | On to: Stage 4